Puddle flange recess. Why the flange sits flush.
·1 min read·FORSPEC Technical Team
The short version
- The wet-area standard requires the flange to be recessed into the floor. It never sits proud.
- A proud flange makes a ridge around the waste, so water sits on the membrane and never reaches the pipe.
- The recess is made before the membrane, in concrete and in sheet floors alike.
The flange is only a few millimetres thick. Set on top of the floor, those few millimetres are enough to hold a ring of water around the waste for the life of the bathroom.
What the standard asks for
- The flange is recessed into the substrate so it finishes flush.
- It is sealed to the pipe and fixed so it cannot move.
- A bead of sealant is tooled where it meets the floor.
- The membrane is then bonded onto the flange.
On concrete
The recess is formed when the slab is poured, or cut in afterwards. Cut it before the primer, vacuum it out, and bed the flange so its rim is level with the floor around it.
On a sheet floor
A flange screwed on top of a sheet floor sits proud, which the standard does not allow. The recess has to be formed in the floor sheet around the pipe, before the membrane. On timber, particleboard and plywood floors the code also asks for the whole bathroom floor to be waterproof, so this join carries more than it does on concrete.
The check
- Lay a straight edge across the flange. It should not rock.
- Push on the flange. It should not move.
- Look for the sealant bead all the way round.
- If any of the three fails, stop before priming.
All five rules for the flange are in puddle flanges: what AS 3740 requires.
The drawing

Where this comes from
- AS 3740:2021: 4.3.1
- NCC Housing Provisions: 10.2.3
Standards are summarised in FORSPEC's own words as a guide. Read the standard itself and your project documents before you build.
Systems, products and drawings
Got a job this applies to?
Send the drawings or a few photos. FORSPEC comes back with the system, the details and the products for your job, within 6 business hours.
On site with FORSPEC
@forspec.pc on Instagram →More news
All news →The month in waterproofing. In one email.
Code and standards changes, new products, new test reports and jobs from site. Once a month. No sales emails.



▶ 3.2K