A membrane tested for the job
The membrane must comply with AS 4654.1 for the way it is used. Class III stretches 300% or more. ACTFLEX 929 SL, 929 HV and 5000 are Class III.
AS 4654.2 cl 2.3 · AS 4654.1 App AExternal balconies, podiums and decks that get tiled, screeded or paved over. Prime, detail the junctions, lay a Class III membrane, screed to falls, then the finish.

Each layer with the one figure that matters, from its data sheet. Tap a layer to see why it is there.
PrimerACTFLEX 700 PU4 to 6 m² per litre · one coatPolyurethane primer under the 929 membranes, about 60 microns dry. Touch dry in 30 minutes at 20°C; put the membrane on within 24 hours. Where the slab reads over 4.5% moisture, prime with two coats of ACTFLEX EP250 instead.
Sealant and filletsACTFLEX 75FC15 x 15 mm fillet at every junctionPolyurethane sealant used with the 929 membranes for the fillet at each change of plane and for joints. The membrane goes over it after 1 to 2 hours. 600 mL sausage.
Membrane for the floorACTFLEX 929 SL1.2 mm in 2 coats · 15 L ≈ 8 to 10 m²Self-levelling polyurethane for balconies, terraces and podiums. Class III to AS 4654.1 (Report 429-3) with 756% elongation. Two coats at 0.7 mm wet each, 24 to 48 hours apart. Full cure at 48 hours, then a 24-hour flood test.
Membrane, high-viscosity gradeACTFLEX 929 HV1.2 mm in 2 coats · recoat in 4 to 6 hThe thicker grade of the same polyurethane membrane, Class III to AS 4654.1. The same 1.2 mm film in two coats, about 10 m² from a 15 L pail. Recoat within 24 hours.
Sheet membrane optionACTFLEX 500075 mm laps, side and endSelf-adhesive sheet membrane, Class III to AS 4654.1 (NATA Report 373) with 374% elongation. Goes on concrete at least 28 days old, primed with EP250.
Screed to fallsSCREED X35 mm over the membrane · tile from 12 hRapid structural screed. Over FORSPEC membranes it goes down unbonded at 35 mm with mesh, on a double slip sheet, or bonded at 10 mm. Foot traffic in 2 to 3 hours and tiling from 12 hours.
Tile adhesiveACTFLEX BIOSETC2TE S1 · grout from 24 hFull coverage and back-buttering on external work. A 20 kg bag covers about 4 to 4.5 m² with a 10 mm notch. Grout from 24 hours.
Houses follow AS 4654.1 and AS 4654.2. Concrete balconies on apartments also get the NCC's own numbers once NCC 2025 applies.
The membrane must comply with AS 4654.1 for the way it is used. Class III stretches 300% or more. ACTFLEX 929 SL, 929 HV and 5000 are Class III.
AS 4654.2 cl 2.3 · AS 4654.1 App AWater must reach the outlet with none left standing. The fall is in the slab, or in a screed under the membrane, never only in the topping above it.
AS 4654.2 cl 2.5.2On concrete balconies of Class 2 to 9 buildings: a 1:80 fall in the slab itself, a 70 mm step-down, a 70 mm hob, and the membrane directly on the slab. Not for houses.
NCC 2025 Vol One F1D4, F1D7The membrane turns up high enough above the finished surface that wind-driven water cannot get over it. The standard's guide heights run from 40 to 180 mm by wind class.
AS 4654.2 cl 2.8.1.1, App AA sub-sill flashing at every door. The membrane turns down into each outlet and overflow. Over a structural joint it stops, or runs unbonded for 100 mm.
AS 4654.2 cl 2.8.3, 2.9, 2.10An unbonded screed sits on a double slip sheet, so it cannot rub on the membrane. On completion the membrane is inspected or tested before it is covered.
AS 4654.2 cl 2.15.2, 2.16A plain-English summary, not the standard. Ask the certifier which NCC edition your job is under, or send us the job.A summary, not the standard. Check the current documents for your job.
TDS and SDS open straight from the card.






Each FORSPEC detail is modelled in 3D so the site team sees the build-up for balcony & podium waterproofing before anyone opens a pail. Send the job and we model yours.




Send the drawings or a few photos. A FORSPEC rep comes back with the system, the CAD details and a 3D of your job.
Send us your job →1 standard detail for balcony & podium waterproofing. Open one to view it and download the PDF and DXF.
Prime the concrete with ACTFLEX 700 PU, form a 15 x 15 mm fillet at every junction, then apply two coats of ACTFLEX 929 SL to 1.2 mm dry. After 48 hours, flood test for 24 hours. Then screed to falls with SCREED X and tile with ACTFLEX BIOSET.
ACTFLEX 929 SL uses 1.4 L/m² over two coats to reach 1.2 mm dry. A 15 L pail covers 8 to 10 m² in practice.
ACTFLEX 929 SL reaches full cure 48 hours after the second coat. Flood test it for 24 hours at 50 mm, then cover it. SCREED X takes tiles from 12 hours.
AS 4654.1 sorts membranes by stretch: Class I under 60%, Class II from 60 to 299%, Class III 300% or more. ACTFLEX 929 SL, 929 HV and 5000 are all Class III.
SCREED X goes down unbonded at 35 mm over FORSPEC membranes, with mesh and a double slip sheet, or bonded at 10 mm. The 35 mm is the FORSPEC system figure from the SCREED X data sheet.
They apply to concrete balconies, roofs and podiums on Class 2 to 9 buildings such as apartments, not to houses. New South Wales and Queensland adopt NCC 2025 from 1 May 2027. Ask the certifier which edition your job is under.
1 to 2 hours after the ACTFLEX 75FC fillet is formed.
ACTFLEX 700 PU, in one coat. Where the slab reads over 4.5% moisture, prime with two coats of ACTFLEX EP250 instead.
Drawings, photos or a description. A FORSPEC rep comes back with the system, the spec clause, CAD details and a 3D visual within 6 business hours.