AS 4654 stops at ground level
AS 4654.1 and AS 4654.2 cover membranes above ground only. A basement wall or lift pit cannot be specified 'to AS 4654'.
AS 4654.2 cl 1.1Pre-applied sheet under the slab and against the walls, cementitious tanking where the concrete is already cast, a waterstop in every construction joint and drainage cell against the backfill.

Each layer with the one figure that matters, from its data sheet. Tap a layer to see why it is there.
Pre-applied sheet membranePREFLEX 30001.7 mm · 1 x 20 m and 2 x 20 m rollsLaid before the pour so the concrete bonds to it. Pour within 56 days of laying, or 42 in hot weather. Turn it up the formwork 300 to 400 mm.
Self-adhesive sheet for cast wallsACTFLEX 500075 mm laps, side and endSelf-adhesive sheet with 374% elongation (NATA Report 373). Goes on concrete at least 28 days old, primed with EP250.
Cementitious tankingACTFLEX 988 CWP1.5 mm in 3 coats · 7 days to cureTwo-part cementitious membrane for walls and slabs already cast. Three coats with AT-MESH to 1.5 mm dry. A 20 kg kit covers about 6.4 to 8 m².
PVC waterstop cast into the jointPREBAR PVC WATERSTOP150 to 320 mm wideCast into construction joints. 150 and 200 mm come in 20 m rolls, 250 mm in 15 m and 320 mm in 12 m. Lengths are joined by welding at 190 to 200°C.
Swelling waterstopPRESWELL HYDROPHILIC WATERSTOPSwells 400 to 500%Hydrophilic rubber strip, 20 x 10 mm, in 10 m rolls. It swells when water reaches it and seals the joint from inside.
Drainage cell against the backfillHIFLOW DRAINAGE CELL15 mm · 22.5 m² a rollDimpled drainage sheet in 15 x 1.5 m rolls. The geotextile faces the soil. Fix it only above the membrane termination, never through the membrane.
Stops a live leakACTFLEX HYDROPLUGSets in 2 to 4 minutesRapid-setting plug pressed into a chase cut square, at least 20 x 20 mm, never a V. Final set is within 10 minutes. A 5 kg pail does about 6 m of chase.
There is no Australian Standard for below-ground membranes. The data sheets and the engineer's design carry the job.
AS 4654.1 and AS 4654.2 cover membranes above ground only. A basement wall or lift pit cannot be specified 'to AS 4654'.
AS 4654.2 cl 1.1The one document on below-ground waterproofing is a selection guide, not a compliance standard, and it sets almost no figures.
ISO/TS 18734:2026 (guidance)Where the engineer designs to AS 3735, every joint takes its movement and stays liquid-tight, and the concrete is kept moist for at least 7 days.
AS 3735 cl 5.2.2, 6.1.1A plain-English summary, not the standard. Check the current documents for your job, or send us the job.A summary, not the standard. Check the current documents for your job.
TDS and SDS open straight from the card.







Each FORSPEC detail is modelled in 3D so the site team sees the build-up for below-ground waterproofing & basement tanking before anyone opens a pail. Send the job and we model yours.





Send the drawings or a few photos. A FORSPEC rep comes back with the system, the CAD details and a 3D of your job.
Send us your job →11 standard details for below-ground waterproofing & basement tanking. Open one to view it and download the PDF and DXF.
BGL001Retaining Wall System1Standard detail · PDF and DXF
BGL002Retaining Wall System2Standard detail · PDF and DXF
BGL005Lift Pit Negative SideStandard detail · PDF and DXF
BGL008Retaining Wall FootingStandard detail · PDF and DXF
BGL009Retaining Wall Suspended SlabStandard detail · PDF and DXF
BGL010Retaining Wall Base SlabStandard detail · PDF and DXF
BGL011Lift Pit Base to Strip Footing CJStandard detail · PDF and DXF
CJL001Cold JointStandard detail · PDF and DXFLay PREFLEX 3000 over the blinding and up the formwork, turned up 300 to 400 mm, then pour onto it. The concrete bonds to the sheet. Pour within 56 days of laying, or 42 in hot weather.
PREFLEX 3000 sheet is 1.7 mm. ACTFLEX 988 CWP goes on in three coats to 1.5 mm dry, with AT-MESH.
PREBAR PVC waterstop is cast into the joint and comes 150 to 320 mm wide. PRESWELL is a 20 x 10 mm strip that swells 400 to 500% when water reaches it.
A 20 kg kit covers about 6.4 to 8 m² at 1.5 mm dry over three coats. Leave it 7 days to cure below ground.
No. AS 4654.1 and AS 4654.2 cover above-ground membranes only. Below ground the job rests on the engineer's design and the membrane data sheet.
Never butt the ends. Lay them side by side for 15 mm. The one place tie wire is used is around a pile cap, where PRESWELL is tied to the reinforcing bars.
Drawings, photos or a description. A FORSPEC rep comes back with the system, the spec clause, CAD details and a 3D visual within 6 business hours.