ACTFLEX 747 TC Polyaspartic top coat
Two-component, UV-stable aliphatic polyaspartic polyurea top coat for roofs and floors
UV-stable, colour-stable top coat for exposed roofs, decks and floors. Brush, roll or spray.
ACTFLEX 747 TC coverage, coats and cure times
UV-stable two-component polyaspartic polyurea top coat for exposed roofs, decks and floors. It goes over ACTFLEX 737 PU and other FORSPEC polyurea coatings, or over surfaces primed with ACTFLEX 727 SEP.
- Consumption
- 0.30–0.40 kgper m², per coat, by substrate and film build · TDS p3
- Coverage
- 45–60 m²per 40 kg set, two coats, practical, 10% wastage · TDS p5
- Coats
- 2laid off at right angles to one another · TDS p4
- Dry film
- 0.4–0.5 mmtotal over two coats, 0.2–0.25 mm per coat · TDS p3
- Recoat
- 2–3 honce the first coat is tack free · TDS p3
- Pot life
- 30–40 mintypicalfrom mixing · TDS p3
- Mix ratio
- 1 : 1Part A to Part B by weight, not by volume · TDS p2
- Pack
- 40 kg setPart A 20 kg + Part B 20 kg · TDS p3
- Foot traffic
- 24 hlight foot traffic after the final coat; full cure 4–7 days · TDS p5
From the FORSPEC data sheet, TDS-747TC · Revision 1 · 12 November 2026. Times are at 25°C and 50% relative humidity unless the data sheet says otherwise. Typical = FORSPEC’s own typical value, not a laboratory-certified one.
Where ACTFLEX 747 TC is used
Use it for
- UV top coat over ACTFLEX 737 PU and other FORSPEC polyurea coatings
- Exposed concrete roofs and roof decks
- Metal and colour-steel tile roofing
- Podiums, balconies, walkways and plant decks left exposed
- Floor top coat: garages, workshops, warehouses and showrooms
- Water storage and sewage tanks and treatment structures, not potable
Know before you start
- Not for potable water contact
- Not straight onto a bare surface: prime first with ACTFLEX 727 SEP
- Not below 5°C or above 35°C, in rain, or in the evening or overnight in winter
- Not over silicone, bitumen or coatings that are not sound and fully bonded
How to apply ACTFLEX 747 TC
- 01
Prepare
Surface flat, hard, dry and clean. Concrete cured 28 days, ground or captive-blasted to an open profile and vacuumed. Render and screed cured 7 days. Abrade and degrease metal and existing coatings.
- 02
Prime
Over ACTFLEX 737 PU inside its 12 hour overcoat window, no primer. Everywhere else, and beyond that window, prime with ACTFLEX 727 SEP at 0.3–0.35 kg/m² and top coat within 24 hours of full dry.
- 03
Mix
Weigh Part A and Part B at 1 : 1 by weight. Mix by machine at low speed until uniform, scraping the sides and base. High speed traps air and causes pinholes. Use within 30 to 40 minutes.
- 04
First coat
Brush, roll or spray at 0.30 to 0.40 kg/m². Lay it off in one direction with full, even coverage and no misses, runs or ponding.
- 05
Second coat
Once the first coat is tack free, 2 to 3 hours at 25°C and 50% RH, lay the second coat off at right angles to the first. Total dry film is 0.4 to 0.5 mm.
- 06
Cure
Light foot traffic 24 hours after the final coat. Full cure and full performance take 4 to 7 days, longer below 10°C. Water immersion only after full cure.
A short guide from the data sheet. Read the full ACTFLEX 747 TC TDS before you start.
Drawings for the systems it goes in
FORSPEC standard details as PDF and DXF. Each sheet is a generic detail: the specification names the products.
ACTFLEX 747 TC test reports and compliance
- Accelerated weathering
- 1500 hours: powdering level 0, discolouration level 1, no blistering, no crackingManufacturer test data, typical (FORSPEC R&D, rated to GB/T 1766)
- Tensile strength
- 10 MPa or greaterManufacturer test data, typical (FORSPEC R&D to GB/T 16777)
- Elongation at break
- 300% or greaterManufacturer test data, typical (FORSPEC R&D to GB/T 16777)
- Tear strength
- 40 N/mm or greaterManufacturer test data, typical (FORSPEC R&D to GB/T 16777)
- Low-temperature bending
- No cracking at -35°CManufacturer test data, typical (FORSPEC R&D to GB/T 16777)
- Waterproofness
- Impermeable at 0.3 MPa held for 120 minutesManufacturer test data, typical (FORSPEC R&D to GB/T 16777)
Results as stated in the data sheet, TDS-747TC · Revision 1 · 12 November 2026. Warranty up to 25 years, depending on the system: ask FORSPEC which term applies to your system.
ACTFLEX 747 TC questions
Is ACTFLEX 747 TC a roof or a floor top coat?
Both. It is the UV top coat over FORSPEC polyurea roof and deck systems, and a colour-stable top coat for floors such as garages, workshops, warehouses and showrooms, over primed concrete or a sound FORSPEC floor coating.
How much do I need?
Allow 0.30 to 0.40 kg/m² per coat, in two coats. In practice a 40 kg set covers 45 m² at 0.40, 51 m² at 0.35 and 60 m² at 0.30 kg/m² per coat, with 10% allowed for wastage. The 0.4 to 0.5 mm dry film is what counts.
Do I need a primer?
Not over ACTFLEX 737 PU inside its 12 hour overcoat window. On concrete, render, masonry, metal and sound existing coatings, or once that window has passed, prime with ACTFLEX 727 SEP first.
How long between coats, and when can I walk on it?
Recoat after 2 to 3 hours at 25°C and 50% RH, once the first coat is tack free, so both coats go on the same day. Light foot traffic is 24 hours after the final coat. Full cure is 4 to 7 days.
Is it UV stable?
Yes. It is an aliphatic polyaspartic made for permanent exposure. After 1500 hours of accelerated weathering it recorded powdering level 0 and discolouration level 1, with no blistering and no cracking. Typical FORSPEC R&D values.
How long does it keep?
Shelf life is 6 months unopened, shorter than the rest of the range, so order to the programme. It may crystallise in cold storage. Warm the drums with heating belts until uniform, never by direct flame.
ACTFLEX 747 TC data sheet
Always work from the current data sheet. Every FORSPEC TDS and SDS →
Specify it. Or buy it.
Send the drawings or photos and FORSPEC comes back with the system, the details and the quantities. Or find a FORSPEC stockist for ACTFLEX 747 TC.