Pool waterproofing. Detailed the right way.

1 min readFORSPEC Technical Team

The short version

  • A concrete pool coated in ACTFLEX 988 CWP, with every junction coved and every penetration detailed.
  • Three coats to 1.5 mm, with ACTFLEX AT-MESH bedded into the wet first coat and fully covered.
  • A pool is filled no earlier than 10 days after the final coat.
FORSPEC drawing of a pool wall to floor junction: 35 by 35 mm cove, bandage bedded in the first coat, three coats of membrane
The pool junction: cove, bandage in the first coat, three coats.

A pool shell is all corners: wall to floor, step to wall, pipe through wall. The membrane is only as good as those junctions.

FORSPEC on Instagram · 8 Nov 2026A pool in ACTFLEX 988 CWP with AT-MESHLoads when you tap

What good detailing looks like

The figures

Coats in pools and tanks
Three, with AT-MESH
Dry film
1.5 mm
Recoat
After 4 to 6 hours
Coverage
About 6.4 to 8 m² per 20 kg kit at 1.5 mm
Fill
At least 10 days after the final coat

Where this comes from

Email thisNewsletter

Systems, products and drawings

● Your job next

Got a job this applies to?

Send the drawings or a few photos. FORSPEC comes back with the system, the details and the products for your job, within 6 business hours.

On site with FORSPEC

@forspec.pc on Instagram →

More news

All news →
● The FORSPEC Brief · monthly

The month in waterproofing. In one email.

Code and standards changes, new products, new test reports and jobs from site. Once a month. No sales emails.

One email a month. Unsubscribe in one click. We never share your address.

Send us your job →☎