(02) 8021 3517 Send your job →
SCREED X pack
● TDS-SCREEDX · Rev 3 · 12 November 2026

SCREED X Rapid screed

Rapid structural screed with Mineralcore technology

Pre-blended 30 MPa screed. Walk on it in 2 to 3 hours, tile from 12 hours.

30 MPaTile from 12 hJust add water
16–18 kg/m²Coverage
≈ 1.15–1.20 m²Per bag
10–100 mmThickness
2–3 hWalk on
12 hTile from
24 hMembrane from
● Explainer

How SCREED X goes on

● The numbers

SCREED X coverage, coats and cure times

Factory-blended rapid screed: just add water. It builds 10 to 100 mm as a bonded, unbonded or floating screed, including over underfloor heating.

Coverage
16–18 kg/m²per 10 mm of thickness · TDS p2
Per bag
≈ 1.15–1.20 m²one 20 kg bag at 10 mm thick · TDS p2
Thickness
10–100 mmbonded, unbonded and floating screeds · TDS p2
Walk on
2–3 htypicalfoot traffic · TDS p2
Tile from
12 htypicalafter placing · TDS p2
Membrane from
24 htypicalonce residual moisture is below 4.5% · TDS p4
Strength
30 MPatypicalat 28 days; 17 MPa at 1 day · TDS p2
Water
1.2–1.4 Lper 20 kg bag, never more · TDS p2
Apply at
5–30°Cair and surface · TDS p2

From the FORSPEC data sheet, TDS-SCREEDX · Revision 3 · 12 November 2026. Times are at 25°C and 50% relative humidity unless the data sheet says otherwise. Typical = FORSPEC’s own typical value, not a laboratory-certified one.

● Which one

SCREED X or FORCEM SCREED BINDER?

SCREED X is pre-blended: just add water. FORCEM SCREED BINDER is the binder you mix with graded sand and water on site. The FORCEM SCREED BINDER data sheet says to use SCREED X where a thinner screed or a faster return to service is needed.

SCREED XFORCEM SCREED BINDER
What goes in1.2 to 1.4 L of water per 20 kg bag1.2 to 1.4 L water per 20 kg bag20 kg of binder to 100 kg of graded sand (1 : 5 by weight), plus water20 kg binder to 100 kg graded sand, plus water
A 20 kg bag at 10 mm thick (theoretical, before wastage)About 1.15 to 1.20 m²About 1.15 to 1.20 m²About 6.1 m², with its 100 kg of sandAbout 6.1 m², with 100 kg sand
Working timeAbout 60 minutesAbout 60 minAbout 90 to 120 minutesAbout 90 to 120 min
Foot traffic2 to 3 hours2 to 3 hLight foot traffic at about 8 hoursLight, about 8 h
TilingFrom 12 hoursFrom 12 hFrom 24 hours, moisture verifiedFrom 24 h, moisture verified
Waterproofing membraneFrom 24 hours, moisture verifiedFrom 24 h, moisture verifiedFrom 24 hoursFrom 24 h
Floating screed, minimum45 mm45 mm55 mm55 mm
Unbonded screed, minimum40 mm; 35 mm over FORSPEC membranes, with mesh and a double slip sheet40 mm; 35 mm over FORSPEC membranes, with mesh and a double slip sheet40 mm; 35 mm with the ACTFLEX 300 and FIBRE X enhanced mix40 mm; 35 mm with the ACTFLEX 300 and FIBRE X enhanced mix
Flexural strength at 28 days (typical)5 MPa5 MPa4.5 MPa4.5 MPa
Apply at (air and surface)5 to 30°C5 to 30°C5 to 35°C5 to 35°C
Product pageSCREED XFORCEM SCREED BINDER

The same on both data sheets: 10 to 100 mm thick, and 17, 25 and 30 MPa compressive strength at 1, 7 and 28 days (FORCEM SCREED BINDER at its standard 1 : 5 mix). The two work together too: a bonded SCREED X screed is laid into a slurry coat mixed from FORCEM SCREED BINDER and ACTFLEX 300. Times and strengths are typical, at 25°C and 50% relative humidity. Each product's data sheet governs.Same on both: 10 to 100 mm thick, 30 MPa compressive at 28 days (FORCEM SCREED BINDER at its standard 1 : 5 mix). A bonded SCREED X screed is laid into a FORCEM SCREED BINDER and ACTFLEX 300 slurry. Times and strengths are typical, at 25°C and 50% relative humidity. Each product's data sheet governs.

● Real jobs

SCREED X on site

Screeding at Kyle Bay
Mixing and laying

More FORSPEC jobs

● Is it right for the job

Where SCREED X is used

Use it for

  • Bonded screeds over prepared concrete, from 10 mm
  • Unbonded screeds over FORSPEC membranes, from 35 mm
  • Floating screeds over insulation and acoustic layers, from 45 mm
  • Screeds with underfloor heating
  • Screed repairs, ramps and build-up
  • Under tiles, waterproofing and resilient flooring

Know before you start

  • Unbonded screeds under 35 mm need written FORSPEC approval
  • Never add more than 1.2 to 1.4 L of water per bag or re-temper a stiff mix
  • Do not use a free-fall drum mixer
  • The substrate needs a tensile pull strength of at least 1.5 MPa
● On site

How to apply SCREED X

  1. 01

    Prepare

    Sound, clean concrete, ground or shot-blasted where smooth, vacuumed. Lightly dampen absorbent surfaces with no free water left on them.

  2. 02

    Bond or separate

    Bonded: brush on a slurry of 3 parts FORCEM SCREED BINDER to 2 parts ACTFLEX 300 by weight and lay the screed into it wet. Unbonded over a membrane: lay over a double slip sheet, laps 200 mm.

  3. 03

    Mix

    1.2 to 1.4 L of clean water in the mixer first, then the full 20 kg bag. Mix 3 to 4 minutes in a forced-action or paddle mixer to a semi-dry mortar.

  4. 04

    Place

    Spread, compact and float within the 60-minute working time. Compact solidly: that is what develops the strength.

  5. 05

    Joints

    Compressible strip at walls and columns. Cut control joints to one-third of the screed depth while workable. Carry substrate movement joints through the screed.

  6. 06

    Cure

    Protect from sun, wind and frost. Walk on it after 2 to 3 hours, tile from 12 hours, and apply a membrane once moisture is below 4.5%, from 24 hours.

A short guide from the data sheet. Read the full SCREED X TDS before you start.

● Calculator

How many bags of SCREED X do I need?

Pre-blended screed, 20 kg bag

Build-up
Allow for waste

The sum uses 18 kg per m² for every 10 mm, the top of the data sheet's 16 to 18 kg range, so one 20 kg bag covers about 1.11 m² at 10 mm. The data sheet's typical yield is 1.15 to 1.20 m² a bag; the calculator works to the heavier figure so you do not run short. Minimums: bonded 10 mm; unbonded 40 mm, or 35 mm (the Unbonded button) only over a cured, flood-tested FORSPEC membrane with mesh reinforcement and a double 200-micron slip sheet; floating 45 mm.

You need

0 bags

An estimate from the data sheet figures. Check it before you order.

 

Where the figures come from

The sum uses 18 kg per m² for every 10 mm, the top of the data sheet's 16 to 18 kg range, so one 20 kg bag covers about 1.11 m² at 10 mm. The data sheet's typical yield is 1.15 to 1.20 m² a bag; the calculator works to the heavier figure so you do not run short. Minimums: bonded 10 mm; unbonded 40 mm, or 35 mm (the Unbonded button) only over a cured, flood-tested FORSPEC membrane with mesh reinforcement and a double 200-micron slip sheet; floating 45 mm.

  • Consumption: about 16 to 18 kg per m² per 10 mm (18 used). TDS-SCREEDX, R3, 12 Nov 2026, page 2
  • Yield per 20 kg bag: about 11.5 to 12.0 L compacted; 1.15 to 1.20 m² at 10 mm. TDS-SCREEDX, R3, 12 Nov 2026, page 2
  • Minimum thickness: bonded 10 mm; unbonded 40 mm, engineered 35 mm over FORSPEC membranes. TDS-SCREEDX, R3, 12 Nov 2026, page 3
  • Floating screed minimum: 45 mm, over insulation or acoustic layers with mesh reinforcement. TDS-SCREEDX, R3, 12 Nov 2026, page 4
  • Unbonded over a FORSPEC membrane: 35 mm, only over cured, flood-tested FORSPEC membranes with mesh reinforcement and a double 200-micron slip sheet. TDS-SCREEDX, R3, 12 Nov 2026, page 3
  • Pack: 20 kg bag; 50-bag pallet. TDS-SCREEDX, R3, 12 Nov 2026, page 2

More: SCREED X product page · Balconies & podiums system · Screeds & levelling system

All calculators →

Drawings for the systems it goes in

FORSPEC standard details as PDF and DXF. Each sheet is a generic detail: the specification names the products.

● Proof

SCREED X test reports and compliance

Compressive strength, 28 days
30 MPa (Class C30)AS 1012.9, FORSPEC R&D data
Flexural strength, 28 days
5 MPa (Class F5)AS 1012.11, FORSPEC R&D data

Results as stated in the data sheet, TDS-SCREEDX · Revision 3 · 12 November 2026. Warranty up to 25 years, depending on the system: ask FORSPEC which term applies to your system.

● Questions

SCREED X questions

How many bags of SCREED X do I need?

Allow about 16 to 18 kg per square metre for every 10 mm of thickness. One 20 kg bag covers about 1.15 to 1.20 m² at 10 mm, or about 0.29 to 0.30 m² at 40 mm.

How thick can SCREED X be laid?

From 10 mm to 100 mm. Bonded screeds start at 10 mm, unbonded screeds over FORSPEC membranes at 35 mm, and floating screeds at 45 mm.

When can I tile over it?

From 12 hours at 25°C. It takes foot traffic after 2 to 3 hours.

When can I waterproof over it?

Once the residual moisture is below 4.5%, which is from 24 hours at 25°C, checked with a carbide hygrometer.

Do I need to add sand or cement?

No. SCREED X is pre-blended. Add 1.2 to 1.4 L of clean water to each 20 kg bag and nothing else.

Can it go over underfloor heating?

Yes. Place the reinforcement to suit the heating design and bring the heating on gradually after the screed has cured.

● Documents

SCREED X TDS and SDS

Always work from the current data sheet. Every FORSPEC TDS and SDS →

Specify it. Or buy it.

Send the drawings or photos and FORSPEC comes back with the system, the details and the quantities. Or find a FORSPEC stockist for SCREED X.

Send us your job →☎