AS 4654 Parts 1 and 2. Balcony and roof membranes.

4 min readFORSPEC Technical Team

The short version

  • AS 4654.1 is the membrane: the tests it passes, matched to an exposed or a covered job.
  • AS 4654.2 is the job: falls, fillets, upturns, terminations, outlets and what goes on top.
  • Many well-known figures (upturn heights, 1 in 100, 8% moisture, a 50 mm screed) are guide figures, not requirements.

AS 4654 covers membranes outside and above ground: balconies, roofs, podiums. It comes in two parts. Both are 2012 editions, and NCC 2025 still calls up those editions.

Part 1: the membrane

A test report to AS 4654.1 shows the membrane passed those tests. It does not show the balcony was built right. That is Part 2.

Part 2: the job

Substrate
No particleboard outside. A roof tile underlay is not a membrane.
Falls
Water reaches the outlet with none left standing.
Fillets
At every change of plane.
Upturns
High enough above the finished surface that water, wind-driven water included, cannot get over. The requirement gives no number.
Terminations
Over-flashing let into a reglet of at least 15 mm and lapped at least 75 mm. Pressure-seal fixings at 150 mm centres or closer.
Doors
The flashing under the sill is part of the membrane system.
Joints
At a structural joint the membrane stops, or runs over it unbonded for 100 mm.
Outlets
The membrane turns down into the outlet or is fixed to a flange. Every drain has a grate, sump or cage.
Planters
The membrane is sealed to the outlet and taken at least 100 mm above the soil.
Protection
The membrane is protected until it is covered, unless it is an exposed system made to be walked on.

Guide figures, not requirements

Many of the AS 4654.2 numbers people quote sit in notes or in the informative Appendix A. They are good practice and a designer can lean on them, but the standard does not require them.

What NCC 2025 adds

The standard itself has not changed since 2012. What changed is the layer on top. For concrete balconies, roofs and podiums on apartment and commercial buildings, NCC 2025 asks for a fall of at least 1:80 in the structural slab itself (a screed or tile bed does not count, except in planters), the membrane laid straight on the slab, and a finish that either drains down to the membrane or is fixed straight to it. It also adds rules for set-downs at doors, hobs at edges, overflows and where joints sit. When it starts depends on the state: see NCC 2025 waterproofing changes.

The 70 mm set-down in NCC 2025 is a step in the concrete, not the membrane height. The AS 4654.2 upturn is still measured from the finished surface.

Where AS 4654 stops

Where this comes from

Standards are summarised in FORSPEC's own words as a guide. Read the standard itself and your project documents before you build.

General information, correct at the date shown. Not advice for your job.

Email thisNewsletter

Systems, products and drawings

● Your job next

Got a job this applies to?

Send the drawings or a few photos. FORSPEC comes back with the system, the details and the products for your job, within 6 business hours.

On site with FORSPEC

@forspec.pc on Instagram →

More news

All news →
● The FORSPEC Brief · monthly

The month in waterproofing. In one email.

Code and standards changes, new products, new test reports and jobs from site. Once a month. No sales emails.

Pressing Sign me up asks us to email you The FORSPEC Brief, once a month. Unsubscribe in one click. We use your address only to send this newsletter.

Send us your job →☎